ALLIED CRITICAL METALS INC
VILA VERDE
TUNGSTEN-TIN PROJECT
The Vila Verde Project is advancing rapidly towards the execution of its Experimental Mining License with the Portuguese Government (DGEG), having secured positive endorsements from the local municipalities, underscoring strong regional support for the project.
ALLIED CRITICAL METALS INC
VILA VERDE TUNGSTEN-TIN
PROJECT
Project Highlights
Vila Verde Tungsten-Tin Project
- Historical resource of 7.3M tonnes with a cut-off of 0.05% WO3
- 3x Borralha land package size
- Pre-existing quarry operation capable of near-term cash flow, with construction and commissioning intended for 2026 with non-dilutive project financing, quarry permitting would allow for processing 150,000 tpa
- Leverage prior pre-existing quarry operation to fastrack permitting process
- Tailings and alluvial material will supply plant with estimated grade for plant design parameters for average feedstock of 0.21% WO3
- Construction and operations estimated to begin in 2026
- Plant design production capacity of 150,000 tonnes per year, would result in 250 tonnes of WO3 per year under present design parameters. May subsequently increase capacity to 300,000 tpa
- Process: Crushing and grinding, then fed into a gravimetric and magnetic concentration system
- Total estimated CAPEX of Pilot Plant is estimated at $7.9M (+$2.9M for later expansion) intended to be funded through non-dilutionary sources
PERMITTING
- Mineral license being converted from exploration license to an experimental mining
- This allows for up to 150k tpa of mineralized material until the full-scale mining license is granted following completion of the feasibility study
- Quarry permitting will allow for 150k tpa initially with potential to expand up to 300k tpa